PRJ-06 · East Africa
East Africa Emergency Shelter Phase 1
Phase 1 humanitarian shelter — ~300 beds via P2/P1 fast-deploy units with mobile sanitary and P3 command/clinic; 2-week deployment target.

Project summaries illustrate typical export scope and configuration. Client names, exact locations, and figures may be rounded or withheld for confidentiality. Signed BOQ and contract govern actual supply.
Project overview
Phase-1 humanitarian shelter package for ~300 people in East Africa, combining P2 folding and P1 quick-assembly accommodation with mobile sanitary groups and P3 command / clinic points.
The deployment target was two weeks from site access. WASH, command and the first shelter zone were prioritised before the remaining accommodation.
Scope & scale
| Metric | Value |
|---|---|
| Beds | ~300 |
| Deployment target | 2 weeks from site access |
| Systems | P2 / P1 shelter; P3 command and clinic |
| Services | Mobile sanitary / minimum WASH |
Configuration summary
| Module | Quantity | System | Notes |
|---|---|---|---|
| SHELTER | ~180 beds | P2 | Rapid family / small-room units |
| SHELTER | ~120 beds | P1 | Standard multi-bed rooms |
| M-SAN | Mobile groups sized for Phase 1 | P1 | WASH priority |
| M-OFF | 2 command units | P3 | Registration + coordination |
| M-CLN | 1 primary-care point | P3 | Triage / first aid |
| M-STR | 2 distribution stores | P1 | — |
Building systems & materials
- —P2 folding units prioritised for first occupancy; P1 quick-assembly kits increased bulk bed and sanitary capacity.
- —P3 expandable units provided larger command and clinical floor areas after rapid deployment.
- —Adjustable supports used only after bearing-surface and temporary wind checks.
Site & phasing
Module IDs on the delivery list matched shelter zones so mixed batches could be directed without resorting.
| Wave | Priority content | Operational result |
|---|---|---|
| 1 | Sanitary + command + first P2 shelter | Registration, WASH and first occupancy |
| 2 | Remaining P2/P1 shelter | Reach ~300-bed capacity |
| 3 | Clinic + stores + service completion | Complete Phase-1 operations |
Schedule
- —Days 1–3: access, bearing surface, drainage and zone marking by site team.
- —Days 3–7: command, sanitary and first P2 shelter deployed.
- —Days 7–14: remaining P2/P1 shelter, clinic and stores completed.
Constraints & approach
- —Incomplete infrastructure: WASH and minimum power interfaces were treated as first-order dependencies.
- —Mixed dispatch: priority components went first for early occupancy while bulk shelter followed in batch 2.
- —Temporary foundations: placement remained subject to bearing, drainage and wind checks.
- —Clinical scope: equipment and medical gases were provided by the response agency.
Gallery

Typical specifications for reference only. Final dimensions, materials and quantities per signed drawings and order.