PRJ-04 · Latin America
Latin America Wind Farm Site Camp
Wind farm site camp for ~120 workers — P1 dormitories with a P4 welded relocatable control office, 3-batch delivery; the P4 office moves as a complete box to the next operator site.

Project summaries illustrate typical export scope and configuration. Client names, exact locations, and figures may be rounded or withheld for confidentiality. Signed BOQ and contract govern actual supply.
Project overview
Temporary camp for a multi-site wind farm construction programme with a peak workforce of ~120. The package combines P1 accommodation and welfare blocks with a P4 welded control office that moves as a complete box to the operator's next site.
The three-batch plan was aligned to civil works, turbine erection and commissioning. Permanent roads, foundations and utility mains remained in buyer scope.
Scope & scale
| Metric | Value |
|---|---|
| Beds | ~120 |
| Delivery batches | 3 |
| Primary systems | P1 dorm / welfare + P4 control office |
| Reuse plan | P4 office lifted and transferred to the next operator site |
Configuration summary
| Module | Quantity | System | Notes |
|---|---|---|---|
| M-DORM | 6 × ~20 beds | P1 | Single-storey strips |
| M-OFF | 1 × 72 m² | P4 | Control + document room; reusable as a complete box |
| M-CANT | 1 × 90 m² | P1 | Staggered dining |
| M-SAN | 2 × 40 m² | P1 | Gender-separated |
| M-GUA | 1 | P4 | Relocatable gate unit |
| M-PWR | 1 shell | P1 | Electrical equipment by buyer package |
Building systems & materials
- —P1 quick-assembly dormitory, dining and sanitary blocks; P4 welded relocatable control and guard units.
- —Envelope and corrosion coating selected against signed wind, rainfall and site-corrosion data.
- —M-PWR supplied as shell only; inverter and switchgear remained in the electrical package.
Site & phasing
Lifting access was reserved for the P4 office and guard units; P1 dormitory rows kept a dismantling face and module marks for the next-site component list.
| Batch | Content | Purpose |
|---|---|---|
| 1 | P4 control office + sanitary + first 40 beds | Civil works mobilisation |
| 2 | Remaining P1 dormitory blocks | Turbine erection peak |
| 3 | Canteen + P4 guard + M-PWR shell | Full commissioning camp |
Schedule
- —Batch 1 occupancy preceded the main turbine-delivery window.
- —Batches 2–3 followed erection and commissioning workforce ramps.
- —P4 office and guard were lifted complete; P1 rows were dismantled for transfer after commissioning handover.
Constraints & approach
- —Multi-site reuse: P4 offices and guards selected for repeated whole-box lifting; P1 connections and finishes selected for repeated dismantling.
- —Milestone risk: office, sanitary and first beds protected in Batch 1.
- —Exposed site: anchorage and wind design governed by signed project data, not a generic camp assumption.
Gallery

Typical specifications for reference only. Final dimensions, materials and quantities per signed drawings and order.