PRJ-04 · Latin America

Latin America Wind Farm Site Camp

Wind farm site camp for ~120 workers — P1 dormitories with a P4 welded relocatable control office, 3-batch delivery; the P4 office moves as a complete box to the next operator site.

Latin America Wind Farm Site Camp

Project summaries illustrate typical export scope and configuration. Client names, exact locations, and figures may be rounded or withheld for confidentiality. Signed BOQ and contract govern actual supply.

Project overview

Temporary camp for a multi-site wind farm construction programme with a peak workforce of ~120. The package combines P1 accommodation and welfare blocks with a P4 welded control office that moves as a complete box to the operator's next site.

The three-batch plan was aligned to civil works, turbine erection and commissioning. Permanent roads, foundations and utility mains remained in buyer scope.

Scope & scale

MetricValue
Beds~120
Delivery batches3
Primary systemsP1 dorm / welfare + P4 control office
Reuse planP4 office lifted and transferred to the next operator site

Configuration summary

ModuleQuantitySystemNotes
M-DORM6 × ~20 bedsP1Single-storey strips
M-OFF1 × 72 m²P4Control + document room; reusable as a complete box
M-CANT1 × 90 m²P1Staggered dining
M-SAN2 × 40 m²P1Gender-separated
M-GUA1P4Relocatable gate unit
M-PWR1 shellP1Electrical equipment by buyer package

Building systems & materials

  • —P1 quick-assembly dormitory, dining and sanitary blocks; P4 welded relocatable control and guard units.
  • —Envelope and corrosion coating selected against signed wind, rainfall and site-corrosion data.
  • —M-PWR supplied as shell only; inverter and switchgear remained in the electrical package.

Site & phasing

Lifting access was reserved for the P4 office and guard units; P1 dormitory rows kept a dismantling face and module marks for the next-site component list.

BatchContentPurpose
1P4 control office + sanitary + first 40 bedsCivil works mobilisation
2Remaining P1 dormitory blocksTurbine erection peak
3Canteen + P4 guard + M-PWR shellFull commissioning camp

Schedule

  • —Batch 1 occupancy preceded the main turbine-delivery window.
  • —Batches 2–3 followed erection and commissioning workforce ramps.
  • —P4 office and guard were lifted complete; P1 rows were dismantled for transfer after commissioning handover.

Constraints & approach

  • —Multi-site reuse: P4 offices and guards selected for repeated whole-box lifting; P1 connections and finishes selected for repeated dismantling.
  • —Milestone risk: office, sanitary and first beds protected in Batch 1.
  • —Exposed site: anchorage and wind design governed by signed project data, not a generic camp assumption.

Typical specifications for reference only. Final dimensions, materials and quantities per signed drawings and order.