PRJ-03 · Middle East
Middle East Oil & Gas Pipeline Camp
Rotational pipeline workforce camp for an international EPC — ~450 beds with worker/management zoning, HSE documentation and 4-batch phasing aligned to welding milestones.

Project summaries illustrate typical export scope and configuration. Client names, exact locations, and figures may be rounded or withheld for confidentiality. Signed BOQ and contract govern actual supply.
Project overview
Rotational workforce camp for an oil & gas pipeline construction project procured by an international EPC. Requires worker/management zoning, HSE document coordination and phased occupancy aligned to welding milestones.
Client: International EPC (confidential). Duration ~30 months. Wall core: rockwool 75–100 mm.
Scope & scale
| Metric | Value |
|---|---|
| Beds | ~450 |
| Delivery batches | 4 |
| Storeys | Single-storey; 2–4 beds/room in management zone |
Configuration summary
| Module | Quantity | System | Notes |
|---|---|---|---|
| M-DORM | ~360 worker beds | P1 | 4–6 beds/room |
| M-DORM | ~90 management beds | P1 | 2 beds/room |
| M-OFF | 180 m² | P4 | Incl. induction room |
| M-CANT | 170 m² | P1 | Cold kitchen zoning |
| M-SAN | Gender-separated + 1 accessible | P1 | — |
| M-CLN | 60 m² | P1 | — |
| M-GUA | 2 | P1 | — |
| M-STR | General storage | P1 | Hazmat not in modular scope |
Building systems & materials
- —Primary P1 dormitory boxes; P4 welded boxes for management offices. Guard posts remain P1.
- —Rockwool 75–100 mm; electrical 220 V / 50 Hz to interface.
- —Modular buildings not ATEX-rated; explosion-proof equipment in dedicated rooms.
Site & phasing
Module location plan provided per batch with on-site numbering.
| Batch | Milestone alignment |
|---|---|
| 1 | Management office + first 120 beds |
| 2 | Main dorm ~200 beds |
| 3 | Canteen + remaining dorm + clinic |
| 4 | Sanitary, storage, guard posts |
Schedule
Phased occupancy tracks pipeline welding spreads — management and first worker beds precede main dorm waves.
Constraints & approach
- —HSE: material certificates and installation method statement for buyer submission.
- —Explosion-proof: modular scope excludes ATEX; dedicated equipment buildings by buyer.
- —Perimeter: dual guard posts; module IDs linked to gate registration SOP.
Gallery

Typical specifications for reference only. Final dimensions, materials and quantities per signed drawings and order.